BUILDING CONSTRUCTION PROJECT REPORT

DEPARTMENT OF BUILDING TECHNOLOGY

GROUP 2

 GENERAL INFORMATION:

GROUP LEADER                          MATRIC NO

OLANRENWAJU GABRIEL                  F/ND/15/3510007

GROUP MEMBERS                      MATRIC NO

ONAMADR AYOMIDE                           F/ND/15/35100
WELEZE EDMOND                              F/ND/15/3510041
ADEBOYE ALEX                                  F/ND/15/3510047
JINODU BARAKAT                              F/ND/15/3510028
APATA MOYOSORE                            F/ND/15/3510030
FALOLA TOBI                                      F/ND/15/3510024
ADEGBENRO TOHEEB                       F/ND/15/3510013
JIMOH ABDUL AZEEZ                         F/ND/15/3510034
SAMUEL TONDE                                  F/ND/15/3510026





THE SITE

Location Of The Site

The site is located at 4, HARVEY ROAD, YABA, LAGOS.

THE PURPOSE OF CONSTRUCTION

Building A Permanent Secretariat  For West African College Of Surgeons




SAFETY OFFICE



We Met The Engineer who took us around the site for observation

 

MACHINERY


There was a CRANE for transferring materials to the top of the building


A temporary power source for the engines

BUILDING COMPONENTS

THE FOUNDATION: It was a pile foundation.
THE COLUMNS: The type of column used was a circular column.
THE WALLS
THE WINDOW AND DOOR OPENINGS


THE SITE OFFICE

The site office was made of MARINE PLY WOOD and AIR CONDITIONS were attached to it.



STORAGE FACILITIES

The storage facility was made of PAN for storing cements, blocks, sand and iron






OTHER THINGS WE SAW ON SITE

* A changing room for the site workers


* An A.C duct/A.C vent 


* A netting for preventing debris from entering the neighbors building


* Some CAUTION signs